Construction Updates

Halstead Drive Street Improvement Project

Halstead Drive reconstruction has started as of July 31, 2017.

Excavation will begin on the section of Highland to the Dakota Rail Trial on Monday, August 28th. Please watch for trail closure signs and directions for a detour on Highland and County Road 110! Sewer and culvert work will also begin on the 28th.

During this work, drivers should expect delays along the west half of the project.  We recommend drivers utilize Halstead Drive eastbound for their travel plans.

Mailboxes have been placed in a bank in front of 7081 Halstead Drive.

Questions? Please contact Matt Havlik, the City Project Construction representative at 612-246-9347, or MHavlik@wsbeng.com ; or City Engineer Paul Hornby at 651-286-8453, or phornby@ci.minnetrista.mn.us ; or the Project Manager Nick Guilliams at 651-286-8468 or NGuilliams@wsbeng.com .

Halstead Drive Newsletter July 3, 2017

Project Update Halstead Drive Street Improvement Project

Mill and Overlay Projects

Updates:

2017 Mill and Overlay notices are going out to residents regarding the work schedule, a summary is as follows:

  1. Monday, August 28 – Milling of the pavement on Kramer Road and Maple Forest
  2. Tuesday, August 29 - Begin removal of damaged curb on Kramer Road and Maple Forest

All work is weather dependent.

2016 Mill and Overlay Update November 10th
2016 Mill and Overlay Update November 4th

2016 Mill and Overlay Update October 27th

2016 Mill and Overlay Update October 21st

2016 Mill and Overlay Update October 6th
2016 Mill and Overlay Newsletter September 28th
2016 Mill and Overlay Update September 22nd
2016 Mill and Overlay Newsletter August 12th
2016 Mill and Overlay Update August 8th
2016 Mill and Overlay Location Map

Tuxedo Road/Enchanted Lane:

***Tuxedo boat launch will be closed beginning September 21, 2017 and remaining closed through the duration of the construction project.***
Newsletter September 11, 2017

Tuxedo Boulevard Construction Update and Detours

Project Update Enchanted Lane and Tuxedo Road Street

Project bids will be considered by Council on Monday August 21, 2017

2016-2017 Crack Fill and Seal Coat Improvement Project

Newsletter:

Newsletter August 24, 2016

Updates:

2017- Contractor plans to start work on Monday, August 21, 2017, unless delayed by weather.  The sealcoat project includes the North and South Saunders Area.

2016 Crack Fill and Seal Coat Update August 9th
2016 Crack Fill and Seal Coat Update August 25th
2016 Crack Fill and Seal Coat Update September 8th

Hennepin County Notices

Hennepin County: County Road 19 Constuction Notice
Hennepin County 10/17/16 Detour Update
Hennepin County CSAH 110, CSAH 6, and CSAH 92 Update:

The schedule for work along CSAH 110 between Sunnybrook and CSAH 6 is as follows;

Now through middle of next week, June 27 th , replacing sections of Curb and Gutter and filling pavement cracks.

June 27 th through July 7 th milling and overlaying roadway. NO WORK Saturday July 1 thru July 4 th .

During work activities roadway will be limited to one lane with flaggers directing traffic, EXPECT DELAYS.

Work on CSAH 110 between CSAH 92 and the west leg of County Road 110 Ext is anticipated to begin following the July 4 th Holiday.

We anticipate this work to be completed before the following Friday, July 14 th .

MetCouncil Projects:

Information is posted if/when it is provided to the City by MetCouncil. For the most up to date information, visit MetCouncil's project page at: https://metrocouncil.org/Wastewater-Water/Projects/Sewer-Planning-Construction-Updates/Projects/MoundCR44-802829.aspx

Mound Area Regional Sewer Improvements

Mound FM Sewer Improvements Handout
Mound Westedge Blvd June 28th Mailing
Metrocouncil Construction Map

Mound Area Sewer and Lift Station Improvements Project Update:

Full closure of Wilshire Blvd. scheduled to begin in early April

Metropolitan Council Environmental Services (MCES), operator of the metro-area wastewater collection and treatment system, will continue to upgrade the sanitary sewer line along Wilshire Blvd. between Maywood Rd. and Bradford Ln. Construction is anticipated to occur from April 2017 through early 2018, with restoration following in the summer/fall 2018.

Wilshire Boulevard is anticipated to close (see map at www.cityofmound.com) at the beginning of April and remain closed through the end of the year. During the closure, traffic will be detoured using Interlachen Rd., Shoreline Dr. and Commerce Blvd.