Mill and overlay requires removal of the top layer (approximately 2 inches) of a street and placement of a new layer of bituminous pavement. The following streets are planned for mill and overlay:

  • Pheasant Crossing
  • Hunters Court
  • Glacier Court
  • Burl Oaks Drive
  • Burl Oaks Court

The City of Minnetrista received bids and awarded the construction contract for the project to Northwest Asphalt, Inc. of Shakopee, Minnesota on May 6th, 2019.

September 18, 2019 Update:

Hydroseed has been installed and work is substantially complete. There may be limited crews in the area working on any remaining punch list items. Thank you for your patience as the City continues to improve its roadway infrastructure

*All construction work is dependent upon weather conditions, temperature and precipitation. If there is inclement weather, the scheduled work will be delayed to the next day.*

Street Improvement Construction Newsletter - June 19, 2019

Project Manager Adam Gadbois 763-762-2803