Below is an update on the Midco Broadband Extension Project. You will find a tentative project timeline and a final design map of the project. As construction of the plant gets closer in your area, Midco will be sending communications directly to residents included in this buildout!

Update March 22, 2022:

Project Schedule:

Overall Timeline for Project: Start Date- December 2021, Complete Date, December 2022

Project Milestone Estimated Start Estimated Complete
Permits Acquired January, 2022 March, 2022
Contractor Selected February, 2022 March, 2022
Project Final Design Completed March, 2022 April, 2022
Purchase and Receive Materials April, 2022 August, 2022
Construction of Plant August, 2022 October, 2022
Test and Activation of System October, 2022 November, 2022
Begin Customer Installation November, 2022

Click here to view the final project design

As always, if you have any questions, please contact Director of Administration Allie Polsfuss at 952-241-2510 (apolsfuss@ci.minnetrista.mn.us) or Andrew Curley from Midco at 605-357-5835 (andrew.curley@midco.com.)

For more information, please visit the project webpage here.