The contractor will continue with concrete curb and driveway placement where applicable for the remainder of the week and early next week. The concrete needs to cure for a minimum of 5 days, so construction activity may slow down for most of next week. Starting the week of May 16th, the contractor will begin to grade and compact the gravel base in preparation for the first layer of new asphalt pavement. Pending favorable weather conditions, paving is scheduled to take place on the 19th and/or 20th. The neighborhood will still be accessible during paving operations. Please drive and walk cautiously through the site and pay close attention to direction from construction personnel and construction signage. As always, please reach out to Matt Havlik or Adam Gadbois with any questions.